Most property project delays in Ghaziabad, Gurgaon: Study

Ghaziabad and Gurgaon, the satellite towns in the National Capital Region (NCR), led in terms of the highest proportion of property projects delayed in the country, which were scheduled for completion in 2008 and onwards, a new study has found.

Both these suburbs have 71 per cent of projects delayed, as against the total number of projects scheduled for completion in 2008 and onwards, a study by real estate research firm PropEquity said.

In Bangalore, 309 of the 575 projects were delayed and the average delay in these projects was nine months. In Pune, 305 of 665 projects were delayed, with an average of eight months. Mumbai came third, with 233 of 501 projects, with an average delay of nine months, the study said.

A lot of developers were diverting funds meant for a project to other projects, hence cash flow was an issue. Their order book was more than what they could actually execute. Many smaller developers jumped into the property sector and they could not complete the projects, resulting in delays,” said Samir Jasuja, founder and chief executive of PropEquity.

Thane, Mumbai and Gurgaon ranked first, second and third, respectively, in terms of percentage price drop in apartments in the country, as economic downturn and dwindling incomes of home buyers impacted property sales and led to a drop in prices. Between May of 2008 and 2009, Thane (a far eastern suburb of Mumbai), Mumbai and Gurgaon witnessed a drop of 22 per cent, 20 per cent and 19 per cent, respectively.